Originally posted by stevenjd
↑
they simply need coin in the coffers to be able to be listed. cash was low after the grafex acquisition.
i assume offtake required before financing. But the schedule all seems pretty compressed, whether financing arrives in tandem or with a delay, cant say.
"Offtake Agreements
Triton also met with Qingdao Tianshengda Graphite (Tianshengda) and Qingdao Haida Graphite (Haida) to progress contractual arrangements to convert the existing non-binding offtake term sheets into binding agreements. Triton and its legal team is currently finalising the detailed terms of the proposed binding offtake agreements. Tianshengda and Haida expressed their confidence in the Ancuabe Project ........... Triton remains confident of finalising the binding offtake agreements within the next month " ie In April
.
EPC And Financing
"Triton’s senior management have recently completed a successful visit to China progressing engineering, procurement and construction (EPC) contracts, debt financing and binding offtake agreements . The Company remains on schedule to make a final investment decision in Q2 2018 with first production anticipated in 2019
The EPC tender process is scheduled to close on 31 March 2018 and Sinosteel and MCC have both confirmed their intention to submit tenders. Technical discussions with both parties confirmed the site location and project design is straightforward and discussions also focussed on opportunities to lower capital cost through leveraging procurement relationships. It is anticipated the award of that tender would be announced in April 2018
to allow the successful contractor to commence work in May 2018.
The potential EPC contractors also coordinated discussions between Triton and leading Chinese financial institutions who reaffirmed the potential for debt financing of up to 85% of the EPC contract sum on competitive terms representing a significant discount to more traditional sources of debt financing. Further, both Sinosteel and MCC have proposed options to defer part of the EPC contract amount for a period of up to 3 years that would reduce the level of upfront financing required in 2018."
Expand
Please refer to the Pathway to Production Announcement - this is TON managements commitment