..I liked this information re halts at Salini/NWH 80/20 airport JV tunnel boring machines halt:
also had not quite grasped the value of this contract to NRW is $400 million.
“• Expert review completed – reports being assessed by PTA and PAPL, full tunnelling operations expected to resume as soon as possible
...Guidance:
• In response to the PTA directing the Joint Venture to cease tunnelling activities, the JV is assessing the impact of the temporary halt against schedule and cost,
• The JV is reviewing options with the PTA to ensure the overall project completion date is not impacted,
• Assuming TBM’s are reactivated within the timeframe indicated by the client the delay is not expected to have a material impact on the FY18 results