I thought I will do a break down of today ann and feel free to correct me if I am wrong:
It was a well planned execution to locating the drill positions on the Pular location. Due to the ground sampling carried out in 2016, PNN was able to located areas that showed low and high reading of Lithium. Below some data of interest for PNN-SU-DW-01 (Hole 1):
* Location of hole one has surface sampling in 2011 (by others ) showed a lithium values as high as 257 mg/L from a max depth of 2 m (19/12/2016 ann)
* Borehole showed brine from surface to base of hold 308. 5 m
* Hole one start and finish date: 19/01/2018 - 21/02/2018
* Strong indication shows that assay results for Hole one are possible any time for April.
All in all IMO and DYOR