Tardiness, at best, has cost this Co a lot of time....and money...and credibility...and now a plummeting SP....
* Environmental Study not submitted till Jan...this now appears to be a key factor holding up up ML approval...now very 'costly' in time for ML approval
* ML application late submission...now Co is 'in the mix' with 1000's before them and now approval dependent on Environmental study which was so very late to be submitted...
* Prospectus 'process' has gone from 8-12 weeks in mid December, to 'who knows' how long now....nearly 4 months to prepare this Prospectus has cost months of time here...untenable behaviour and performance by BoDs here
* PFS stated to be completed by Q1...now nearly Q3....due in 'near future...soon'
Tardy is being kind imo....what else have so many exorborant salaries had to do??...
Well oiled 'wishy-washy speel' by TM....heard it all before....same ol' same ol'...and still nothing achieved...joke imo
- Forums
- ASX - By Stock
- VRC
- Ann: CEO Update
Ann: CEO Update, page-2
Add VRC (ASX) to my watchlist
(20min delay)
|
|||||
Last
0.4¢ |
Change
-0.001(12.5%) |
Mkt cap ! $16.63M |
Open | High | Low | Value | Volume |
0.4¢ | 0.4¢ | 0.4¢ | $27 | 7.743K |
Buyers (Bids)
No. | Vol. | Price($) |
---|---|---|
39 | 69769192 | 0.3¢ |
Sellers (Offers)
Price($) | Vol. | No. |
---|---|---|
0.4¢ | 13391021 | 23 |
View Market Depth
No. | Vol. | Price($) |
---|---|---|
6 | 1559831 | 0.004 |
33 | 30514663 | 0.003 |
16 | 20101715 | 0.002 |
10 | 20667001 | 0.001 |
0 | 0 | 0.000 |
Price($) | Vol. | No. |
---|---|---|
0.005 | 14480737 | 14 |
0.006 | 9465480 | 19 |
0.007 | 10780001 | 5 |
0.008 | 5139155 | 8 |
0.009 | 2745744 | 8 |
Last trade - 11.57am 03/12/2024 (20 minute delay) ? |
VRC (ASX) Chart |